UPDATE...

Updates

March 6th - Noon

March 6th - 5PM

March 7th - 3PM

March 8th - 4PM

March 9th - 5PM

March 10th - 5PM

March 11th - 5PM

Construction & Restart Schedule for the Pipeline

 

MIDDLESEX COUNTY UTILITIES AUTHORITY
SEWER LINE BREAK UPDATE: March 6, 2003

5:00 PM
Contact: Richard Fitamant or Tony Cicatiello
732.721.3800

 

  • As of 4 pm, total amount of bypass sewage at the Sayreville Pumping Station was estimated at 335 million gallons

  • The average hourly bypass sewage rate varies from 2.7 to 5.7 million gals/hr; weather is still a major factor in that the volume of sewage and run-off from precipitation is still high
  • The site has been excavated and the pipe is now visible; the sheeting is being put in place to shore-up the soft ground and to allow excavation to continue; placement of the sheeting is taking longer because of weather conditions; contractor has estimated that it will take 24 hours to complete the excavation and pumping out the remainder of the sewage from the pipe
  • By Friday (March 7) afternoon, MCUA should be able to establish the timeline for construction and repair of the line; a best and worst case scenario will be made available
  • Weather is still a factor in the repair process; snow, sleet and rain delay the process but does not stop it; the weekend weather report calls for more rain which will continue the high volume of water coming to the pump station
  • Work is continuing on a 24-hour basis


 

Leadership | Solid Waste Division | Wastewater Division | News | Contact the MCUA