UPDATE...

Updates

March 6th - Noon

March 6th - 5PM

March 7th - 3PM

March 8th - 4PM

March 9th - 5PM

March 10th - 5PM

March 11th - 5PM

Construction & Restart Schedule for the Pipeline

 

MIDDLESEX COUNTY UTILITIES AUTHORITY
SEWER LINE BREAK UPDATE: March 10, 2003

5:00 PM
Contact: Richard Fitamant or Tony Cicatiello
732.721.3800

 

  • As of 12 noon, total amount of bypass sewage at the Sayreville Pumping Station was estimated at 541 million gallons

  • The average hourly bypass sewage rate varies between 1.6 to 3.0 million gals/hr

  • At the break site, the repair of the pipe is completed; the welding of the pipe is completed; the concrete encasement of the pipe is progressing well and should be completed by 6 pm

  • 102” force main filling will commence by 6 pm; the process will take about 24 hours in order to release air from the pipeline and get pressures stabilized in the system

  • Begin backfilling of excavation; portions of steel sheeting to remain in place; replace damaged section of Sayreville 8” sewer line

  • On Tuesday, March 11, at approximately 6 pm, the 102” force main is back into full service; bypass is eliminated

  • On Wednesday, March 12, backfilling and excavation completed; removal of sheeting completed; site graded with seeding to be performed during the spring months; contractor demobilizes

  • Presently, the MCUA plans to utilize both the 72” pipeline and the repaired 102” pipeline so that the sewage volume is contained and only treated sewage from the wastewater treatment plant is discharged to the Raritan River/Bay

  • MCUA’s independent consultant took samples at the Sayreville pump station and in the Raritan River today; all data will be forwarded to DEP; sampling will continue throughout the week

  • Work is continuing on a 24-hour basis



 

Leadership | Solid Waste Division | Wastewater Division | News | Contact the MCUA