UPDATE...

Updates

March 6th - Noon

March 6th - 5PM

March 7th - 3PM

March 8th - 4PM

March 9th - 5PM

March 10th - 5PM

March 11th - 5PM

Construction & Restart Schedule for the Pipeline

 

MIDDLESEX COUNTY UTILITIES AUTHORITY
SEWER LINE BREAK UPDATE: March 9, 2003

5:00 PM
Contact: Richard Fitamant or Tony Cicatiello
732.721.3800

 

  • As of 4 pm, total amount of bypass sewage at the Sayreville Pumping Station was estimated at 495 million gallons

  • The average hourly bypass sewage rate varies between 1.3 to 3.0 million gals/hr; the warm weather continues to cause the snow to melt that produced a larger volume of run-off which required us to bypass sewage at a higher rate than yesterday

  • At the break site, the inspection of the pipeline confirmed that the break was isolated to one section of the pipeline; the approval was given to go forward with the repair; the construction company placed the new pipe during the overnight hours; the new pipe is now being welded to create a water-tight connection, a process that takes approximately 12 hours – work should be concluded around 10 pm today



 